The
Directorate is headed by Chief Engineer BPS-20 officer and located at GEPCO HQ,
The tasks assigned to Technical Directorate GEPCO are:
- Planning and Design of electricity distribution,
sub-transmission and grid stations.
- Procurement of material for these development and
system expansion works.
- Construction of the development and system expansion
works.
The
directorate consists on following Departments:
- Planning & Engineering
- Material Management
- Project Construction
Planning and Engineering Department
The
Planning & Engineering Department headed by Chief Engineer, the think tanks
of GEPCO where the intellectual’s brains..…the Engineers of the company sit to
plan & design the pitches to manage and sustain the existing distribution
system (HT/LT Lines) and plane how to meet with the future requirement of the
company to facilitate the honorable customers of the company. The P&E
department equipped with latest tool and technologies (GIS). GEPCO the 1st
company who mapped all his grids and lines through Geographical Information
System. The area of work as under:
·
To Plan for functional guidance
in all technical activities to ensure efficient and economical operation of the
distribution system.
·
Because of many voltage level and
the many site of equipment available it is not easy matter to decide on most
economical combination.
·
To forecast need for system
expansion to provide adequate and reliable service to valued consumers.
·
Implement standard and
specification of the authority regarding Planning & Engineering.
·
To Administer the issuance of
work order for high tension (H.T) and low tension (L.T) proposals for
augmentation/ rehabilitation of the distribution network under energy loss
reduction and distribution of Power program.
·
To encourage latest technology
for carrying out the analysis of system to get accurate result for evaluation
correct parameters.
·
To know system constraints for
their trouble shooting to minimize system losses.
·
Processing
the applications for New Connections / Reconnections / Load Extensions and Bulk
Supply having load of more than 500 KW (Tariff Categories B – 3, B – 4, C – 2
& C – 3)
·
Approval
& Design of External Electrification of Housing Schemes
·
Approval
& Design of Electrification of Multistory Buildings/Shopping Plazas
·
Preparation
of Distribution System Rehabilitation and extension and issuance of work orders
there of
·
Inspection
of completed work orders
·
Load
flow studies of distribution network
·
Technical
adjudication of tenders for purchase of material
·
Maintenance
of record/data of 11kv feeders
·
Updating
database of 11kv feeders
·
Load
flow studies on Transmission Lines and design/development plans for
Transmission Lines and Grid Stations
·
Inspection
of materials procured for works
Development of standards and specification for
materials/components and systems